The Project
The SMOB project is divided into 7 work-packages, with a total planned duration of 28 months. Officially commencing on 01/09/2012, the expected deadline is the 31/12/2014, according to the constraints of the competitive bid.
WP1 - Logical and conceptual design of the technological platform
WP2 - Creation of the social networking server
WP3 - Creation of the logistics optimization server
WP4 - Creation of the auxiliary applications
WP5 - Creation of graphical user interfaces
WP6 - Integration, testing and validation of the entire platform
WP7 - Dissemination